Updates for the men’s locker room remodel (10/12/15):

  • Updates for the men’s locker room remodel:
  • Floor and ceiling tile completed by the end of this week
  • Millwork installed last week
  • Solid surface tops expected October 19
  • All lighting and fixtures completed this week
  • Whirlpool tile still in process
  • Custom shower doors have been ordered
  • All new body wash, shampoo and conditioner dispensers have been delivered
  • New product schedule to arrive beginning of next week

We anticipate the temporary construction wall to come down by next week allowing for the final push in the project which involves the ceiling grid and tile, lighting, carpet, and skim and paint the dry side of the whirlpool wall tile.